Application and contract
According to the standard terms and conditions for connecting to Elering’s electricity transmission system (hereinafter referred to as the connection conditions), all procedures related to connecting to the transmission system, preliminary feasibility study for connection, and the accompanying data exchange are carried out in the information system for connections egle.ee, in which data on the requested connection and necessary appendices must be submitted.
When submitting a connection application, it must be taken into account that the documents to be submitted should include both the generating unit and the installations related to the generating unit as well as the power lines and substations between the connection point and the generating unit.
If the technical parameters of the generating unit change at a later stage, both the technical solution for connection and the related connection fee may change accordingly.
To receive a connection offer, the client is required to pay the processing fee.
Elering will inform the client of deficiencies in the connection application within five days from the payment of the processing fee. The client has 20 working days from the submission of Elering’s notice to remedy the deficiencies in the connection application.
The connection offer is made to the client within 90 days from the acceptance of a proper connection application. The offer is valid for 60 days, during which a connection contract must be entered into.
NB! According to § 21 (6) of the Grid code on the Functioning of the Electricity System, if the connection agreement terminates before its completion for reasons attributable to the client, except in the case specified in paragraph 7 (the cost of the construction procurement of the cost-based component is more than 2 times more expensive than the cost of the construction procurement originally estimated in the connection agreement), the connection fees will not be refunded to the client.
The connection contract includes:
- locations of the connection and metering point;
- estimated amount of the connection fee and the fee for amendment of the connection conditions and the terms and conditions of payment thereof as well as the calculation thereof;
- technical solution for connection with the basic electrical parameters of the connection point;
- conditions for ensuring grid connection;
- amendment of consumption and/or generation conditions;
- terms and conditions of amendment and termination of the connection contract;
- terms and conditions of the general part of the connection contract;
- deadline for completion of the connection;
- other terms and conditions.
The connection contract is entered into once Elering receives an acceptance of the offer at the latest on the last day of validity of the offer of a connection contract and provided that the client has submitted to Elering all the required data and documents together with the connection application. The singing of the connection contract is considered an acceptance of the offer of a connection contract.
When performing network calculations following the connection applications received from 1 May 2022 onwards, Elering uses a calculation methodology that does not require an additional increase in the transmission capacity of the electricity network when connecting generating and/or consumption-oriented capacities of connection contracts entered into in the same substation at the same voltage to a common connection point. All work to increase the transmission capacity of connection contracts to be merged will remain in force, but the need to establish multiple connection points will cease. If you are interested, please contact the project manager in charge of your connection contract.
Appendices to be submitted upon connection
Tootmissuunalisel liitumisel esitatavad lisad
Tootmissuunalisel liitumisel esitatavad lisad
Tootmissuunalise tootmismooduli või segapaigaldisega liitumiseks või nende tootmis- ja/või tarbimistingimuste muutmiseks tuleb taotlusele lisada:
- Võrguga ühendatava elektripaigaldise rajamist võimaldava planeeringu algatamise või planeeringu kehtestamise otsus;
- Avalikku veekokku rajatava tootmisseadme võrguga ühendamiseks esitab turuosaline võrguettevõtjale koos liitumistaotlusega ehitusseadustiku § 113 priim 1 lõikes 1 sätestatud hoonestusloa või lõikes 1 priim 2 sätestatud meretuulepargi hoonestusloa keskkonnamõju hindamise aruande nõuetele vastavaks tunnistamise otsuse;
- Planeeringu koostamise kohustuse puudumise korral kohaliku omavalituse või muu planeeringu kehtestaja kinnitus, et võrguga ühendatava elektripaigaldise rajamiseks puudub planeeringu koostamise kohustus;
- Asendiplaan, kuhu märgitakse peale elektripaigaldise ja liitumispunkti olemasolev või soovitav asukoht koos koordinaatidega ning kogu liituva kliendi poolt võrguga ühendatav tootmisseade;
- Tagatisraha tasumise maksekorraldus või garantiikiri;
- Muud olulised taotlusele lisatavad lisad, mida taotleja peab vajalikuks esitada (pole kohustuslik).
Tarbimissuunalisel liitumisel esitatavad lisad
Tarbimissuunalisel liitumisel esitatavad lisad
Tarbija või jaotusvõrguettevõtja liitumisel uues liitumispunktis või olemasolevas liitumispunktis tarbimis- ja/või tootmistingimuste muutmisel tuleb liitumistaotlusele lisada:
- Asendiplaan, kuhu märgitakse peale elektripaigaldise ja liitumispunkti olemasolev või soovitav asukoht koos koordinaatidega ning kogu liituva kliendi poolt võrguga ühendatav tootmisseade;
- Elektripaigaldise käivitus- ning seiskamisprotsessi kirjeldus ja prognoositud talituse kirjeldus, märkides ära kõik olulised talitlust mõjutavad asjaolud (juhul kui üksiku tarbija elektrivõrguga ühendatava elektritarviti võimsus on üle 10MW);
- Jaotusvõrguga liitumistaotluse alusel ühendatavate ning juba liidetud tootmismoodulite nimekiri;
- Tagatisraha tasumise maksekorraldus või garantiikiri;
- Muud olulised taotlusele lisatavad lisad, mida taotleja peab vajalikuks esitada (pole kohustuslik).
Juhul, kui liitumistaotluses nõutud andmed on kliendi poolt põhivõrguettevõtjale varasemalt esitatud ning nendes ei ole muudatusi toimunud, võib liituja nõutud materjalid esitamata jätta, viidates varasemale taotlusele või kirjale, mille käigus on nõutud andmed esitatud.